Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International Exam CCP Topic 3 Question 2 Discussion

Actual exam question for AACE International's CCP exam
Question #: 2
Topic #: 3
[All CCP Questions]

You have recently been appointed as the Cost Engineer to oversee process improvement projects for a Discrete Part Manufacturer. You have been asked to calculate the CPI on a project initiated to implement a Value Stream Mapping Initiative. The accountant is only able to provide you with BAC and EAC figures of $ 5000 and 57500 respectively. The CPI is:

unable to be calculated from the information given

Show Suggested Answer Hide Answer
Suggested Answer: A

The Cost Performance Index (CPI) is calculated using the formula:

CPI = BAC / EAC

Given:

Budget at Completion (BAC) = $50,000

Estimate at Completion (EAC) = $57,500

CPI = $50,000 / $57,500 = 0.8696

Since CPI < 1, it indicates that the project is over budget. The correct answer is A. <1.


Contribute your Thoughts:

Stephen
3 months ago
I see your point, Tony. So, the answer would be D) >1 then.
upvoted 0 times
...
Tony
3 months ago
But isn't the CPI always calculated as EV/AC? So, in this case, it would be greater than 1.
upvoted 0 times
...
Theodora
3 months ago
Ha, the accountant really dropped the ball here! Without the actual costs, there's no way to calculate the CPI. A is the way to go.
upvoted 0 times
Reed
2 months ago
Ha, the accountant really dropped the ball here! Without the actual costs, there's no way to calculate the CPI. A is the way to go.
upvoted 0 times
...
Isabella
3 months ago
A) <1
upvoted 0 times
...
...
Aimee
3 months ago
Looks like we need the actual costs and planned costs to figure out the CPI. Going with A on this one.
upvoted 0 times
...
Rhea
3 months ago
I agree, the information given is not enough to determine the CPI. This is a trick question, but I think A is the right answer.
upvoted 0 times
Ernest
3 months ago
I agree, the information given is not enough to determine the CPI.
upvoted 0 times
...
Albina
3 months ago
I think A is the right answer.
upvoted 0 times
...
...
Sylvia
3 months ago
I agree with Shantay, we need more data to calculate the CPI.
upvoted 0 times
...
Shantay
3 months ago
I think the CPI can't be calculated from the given information.
upvoted 0 times
...
Shonda
3 months ago
Hmm, without the actual cost and schedule figures, there's no way to calculate the CPI. This is tricky, but I guess the correct answer is A.
upvoted 0 times
Coleen
3 months ago
It's definitely a tricky situation, but I believe the accountant needs to provide more details for us to accurately calculate the CPI.
upvoted 0 times
...
Suzi
3 months ago
Yes, I think the correct answer is A because we can't determine if it's less than or greater than 1 without the actual cost and schedule data.
upvoted 0 times
...
Viola
3 months ago
I agree, without the necessary information, it's impossible to calculate the CPI.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77