Given this information regarding a Task:
* Planned Start Date: May 14
* Actual Start Date: May 14
* Planned Completion Date: May 20
* Projected Completion Date: May 22
* Percent Complete: 50%
* Duration: 5 Days
* Planned Hours: 8 Hours
* Status: In Progress
If today's date were May 19, what would be the Task's progress status?
In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.
Maybelle
2 months agoWillard
2 months agoAnthony
1 months agoMaia
1 months agoTaryn
1 months agoGene
2 months agoLina
28 days agoDean
1 months agoDenae
1 months agoFloyd
2 months agoJudy
1 months agoJeannetta
1 months agoRefugia
1 months agoMarleen
2 months agoBeckie
2 months agoYong
2 months agoCoral
3 months agoMurray
1 months agoIrma
1 months agoFrance
1 months agoCathrine
2 months agoDominga
2 months agoEva
3 months ago