Adobe Exam AD0-E903 Topic 3 Question 10 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 10
Topic #: 3
[All AD0-E903 Questions]

Given this information regarding a Task:

* Planned Start Date: May 14

* Actual Start Date: May 14

* Planned Completion Date: May 20

* Projected Completion Date: May 22

* Percent Complete: 50%

* Duration: 5 Days

* Planned Hours: 8 Hours

* Status: In Progress

If today's date were May 19, what would be the Task's progress status?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.


Contribute your Thoughts:

Maybelle
2 months ago
I'm just glad the task isn't status 'Abandoned' or 'Terminated'. Now that would be a real problem!
upvoted 0 times
...
Willard
2 months ago
This is a no-brainer. If a task is only 50% done with one day left in the planned schedule, it's definitely A) Behind. Someone needs to get their act together on this project!
upvoted 0 times
Anthony
1 months ago
A) Behind
upvoted 0 times
...
Maia
1 months ago
A) Behind
upvoted 0 times
...
Taryn
1 months ago
A) Behind
upvoted 0 times
...
...
Gene
2 months ago
With the task only 50% complete on May 19, and the planned completion date being May 20, I'd say B) On Time is the correct answer. The task is still on schedule, even if it's projected to finish a couple days late.
upvoted 0 times
Lina
28 days ago
C) At Risk
upvoted 0 times
...
Dean
1 months ago
B) On Time
upvoted 0 times
...
Denae
1 months ago
A) Behind
upvoted 0 times
...
...
Floyd
2 months ago
C) At Risk seems like the right answer here. The task is projected to be completed on May 22, which is after the planned completion date of May 20, so it's at risk of being delayed.
upvoted 0 times
Judy
1 months ago
C) At Risk seems like the right answer here. The task is projected to be completed on May 22, which is after the planned completion date of May 20, so it's at risk of being delayed.
upvoted 0 times
...
Jeannetta
1 months ago
C) At Risk
upvoted 0 times
...
Refugia
1 months ago
B) On Time
upvoted 0 times
...
Marleen
2 months ago
A) Behind
upvoted 0 times
...
...
Beckie
2 months ago
I think the task is at risk because even though it's not yet past the planned completion date, the progress is only at 50%.
upvoted 0 times
...
Yong
2 months ago
I agree with Eva, the task is behind because the projected completion date is after the planned completion date.
upvoted 0 times
...
Coral
3 months ago
If the task is only 50% complete on May 19, but the planned completion date is May 20, then it's definitely behind schedule. The answer has to be A) Behind.
upvoted 0 times
Murray
1 months ago
Let's make sure to adjust the timeline for future tasks to avoid delays.
upvoted 0 times
...
Irma
1 months ago
It's important to keep track of progress to avoid falling behind.
upvoted 0 times
...
France
1 months ago
I agree, the task is definitely behind schedule.
upvoted 0 times
...
Cathrine
2 months ago
A) Behind
upvoted 0 times
...
Dominga
2 months ago
A) Behind
upvoted 0 times
...
...
Eva
3 months ago
I think the task is behind schedule.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77