Adobe Exam AD0-E903 Topic 3 Question 5 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 5
Topic #: 3
[All AD0-E903 Questions]

Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

Show Suggested Answer Hide Answer
Suggested Answer: B

In Adobe Workfront, Condition is the reportable variable that is determined by the relationship between the Planned, Projected, and Estimated Dates. The Condition field reflects whether a project is On Target, At Risk, or In Trouble based on how its actual progress aligns with the planned schedule and dates. It allows project managers and stakeholders to quickly assess the health of the project.


Contribute your Thoughts:

Cordelia
2 months ago
This question is giving me a Condition red. I'm just gonna go with Progress Status and hope for the best!
upvoted 0 times
Evangelina
26 days ago
Let's hope we all made the right choice with Progress Status.
upvoted 0 times
...
Fernanda
29 days ago
I'm not sure, but I'll go with Progress Status too.
upvoted 0 times
...
Jarod
1 months ago
I agree, it seems like the most logical option.
upvoted 0 times
...
Celestina
1 months ago
I think Progress Status is the best choice here.
upvoted 0 times
...
...
Trevor
2 months ago
Hmm, I'm feeling a bit Conditioned to choose B) on this one. But I think Progress Status is the way to go!
upvoted 0 times
...
Chana
2 months ago
This question is a real head-scratcher, but I gotta go with Progress Status. Sounds like the most technical term of the bunch.
upvoted 0 times
Augustine
1 months ago
I'm leaning towards Condition, but Progress Status does make sense in this context.
upvoted 0 times
...
Olga
1 months ago
I think it's Status, but Progress Status does sound more specific.
upvoted 0 times
...
Reuben
1 months ago
I agree, Progress Status seems like the most technical option.
upvoted 0 times
...
...
Brandee
2 months ago
Ooh, this one's tricky! I'm going to go with B) Condition. Sounds like the most comprehensive option to me.
upvoted 0 times
...
Pa
2 months ago
Progress Status, no doubt. Whoever came up with these options must be a real project management pro!
upvoted 0 times
...
Alexis
2 months ago
Status seems like the obvious choice here. Reportable variables are all about the current state of the project.
upvoted 0 times
Mari
1 months ago
Progress Status could also be a good option, but I still think Status is the best choice.
upvoted 0 times
...
Yvonne
1 months ago
Condition doesn't really fit the description.
upvoted 0 times
...
Willis
1 months ago
I agree, Status is all about the current state of the project.
upvoted 0 times
...
Eleni
1 months ago
B) Condition
upvoted 0 times
...
Lisha
2 months ago
I think it's C) Progress Status
upvoted 0 times
...
Celestina
2 months ago
A) Status
upvoted 0 times
...
Madelyn
2 months ago
I think Status is the right answer.
upvoted 0 times
...
...
Janine
2 months ago
Hmm, I'd go with Condition. Gotta keep an eye on those projected dates, you know?
upvoted 0 times
Phyliss
2 months ago
I'm not sure, but I think Status might also be important to keep track of the project's progress.
upvoted 0 times
...
Tabetha
2 months ago
I agree with you, Progress Status seems like the right choice to monitor the projected dates.
upvoted 0 times
...
Dion
2 months ago
I think it's Progress Status. That's the one that tracks the relationship between the planned and estimated dates.
upvoted 0 times
...
...
Floyd
3 months ago
I'm not sure, but I think it could also be A) Status because that also relates to the project's planned dates.
upvoted 0 times
...
Isaiah
3 months ago
I agree with Olive, Progress Status makes sense because it relates to the dates of the project.
upvoted 0 times
...
Fatima
3 months ago
Progress Status, of course! That's the classic way to track project timeline progress.
upvoted 0 times
Marylin
2 months ago
Progress Status, of course! That's the classic way to track project timeline progress.
upvoted 0 times
...
Ozell
2 months ago
C) Progress Status
upvoted 0 times
...
Carey
2 months ago
B) Condition
upvoted 0 times
...
Charlie
2 months ago
A) Status
upvoted 0 times
...
...
Olive
3 months ago
I think the answer is C) Progress Status.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77