APICS Exam CPIM-MPR Topic 3 Question 101 Discussion

Actual exam question for APICS's CPIM-MPR exam
Question #: 101
Topic #: 3
[All CPIM-MPR Questions]

Which of the following actions would most likely lead to an achievable master production schedule?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Lashonda
2 months ago
I bet the answer is B. You can never have too much safety stock. It's like a security blanket for your production schedule.
upvoted 0 times
Roosevelt
26 days ago
User 3: I agree with Roosevelt, A seems like the best option for a achievable master production schedule.
upvoted 0 times
...
Nichelle
1 months ago
User 2: I disagree, I believe the answer is A. Minimizing changes is crucial for a stable schedule.
upvoted 0 times
...
Rozella
1 months ago
I think the answer is D. Customer satisfaction is key.
upvoted 0 times
...
...
Charlie
2 months ago
Minimizing changes before the demand time fence? Sounds like a recipe for disaster. Where's the flexibility?
upvoted 0 times
Art
29 days ago
C) Limiting changes in periods after the planning time fence
upvoted 0 times
...
Jaclyn
1 months ago
B) Keeping safety stock for key subassemblies
upvoted 0 times
...
Chau
2 months ago
A) Minimizing changes in periods before the demand time fence
upvoted 0 times
...
...
Tonette
2 months ago
I believe committing to customer requested shipment dates is crucial for a achievable master production schedule.
upvoted 0 times
...
Shad
2 months ago
Committing to customer requested shipment dates? That's a bold move, Cotton. Let's see if it pays off.
upvoted 0 times
...
Antione
2 months ago
Keeping safety stock for key subassemblies sounds like a smart move to me. That way you're prepared for any last-minute changes.
upvoted 0 times
Sol
2 months ago
D) Committing to customer requested shipment dates
upvoted 0 times
...
Beckie
2 months ago
C) Limiting changes in periods after the planning time fence
upvoted 0 times
...
Tran
2 months ago
B) Keeping safety stock for key subassemblies
upvoted 0 times
...
Rikki
2 months ago
A) Minimizing changes in periods before the demand time fence
upvoted 0 times
...
...
Abraham
2 months ago
I agree with Lenora, keeping safety stock for key subassemblies can also help in achieving the master production schedule.
upvoted 0 times
...
Lenora
2 months ago
I think minimizing changes before the demand time fence is important for a achievable master production schedule.
upvoted 0 times
...
Catarina
3 months ago
I think limiting changes after the planning time fence is the way to go. Stability is key for a master production schedule.
upvoted 0 times
Janessa
3 months ago
Committing to customer requested shipment dates can also help in achieving an achievable master production schedule.
upvoted 0 times
...
Kathryn
3 months ago
I agree, stability is crucial for a master production schedule.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77