APMG-International Exam AgileBA-Foundation Topic 2 Question 15 Discussion

Actual exam question for APMG-International's AgileBA-Foundation exam
Question #: 15
Topic #: 2
[All AgileBA-Foundation Questions]

During which process phase is the Prioritised Requirements List baselined?

Show Suggested Answer Hide Answer
Suggested Answer: B

The Prioritised Requirements List (PRL) is baselined during the Foundations phase. This phase is critical for establishing a clear understanding of the requirements and priorities before the development work begins. Baselining the PRL ensures that there is a formal agreement on the scope and priorities of the requirements, which serves as a foundation for subsequent development iterations.


Business Analysis.pdf, 'requirements validation is carried out to review and agree the requirements documentation...At this point the CIs that describe the requirements are said to be 'baselined''.

Contribute your Thoughts:

Lindy
2 months ago
Wow, they really want to trip us up with this one, huh? Time to put on my thinking cap and make a wild guess. I'll go with C) Evolutionary Development, just for fun.
upvoted 0 times
...
Joseph
2 months ago
I'm going with B) Foundations. It just makes the most sense to me as the phase where the requirements are solidified and approved.
upvoted 0 times
Loreta
25 days ago
I'm not sure, but I'll go with B) Foundations too. It does make sense for the requirements to be finalised at that stage.
upvoted 0 times
...
Page
26 days ago
I think it could also be C) Evolutionary Development, as requirements may evolve during this phase.
upvoted 0 times
...
Jerry
28 days ago
I agree, B) Foundations seems like the right choice for baselining the requirements.
upvoted 0 times
...
...
Alexia
2 months ago
A) Feasibility? Nah, that's too early in the process. The requirements need to be fleshed out first before they can be baselined.
upvoted 0 times
...
Brice
2 months ago
D) Deployment? Really? I don't think that's when the requirements get baselined. Seems more like the final phase to me.
upvoted 0 times
...
Dean
2 months ago
Hmm, I'm not so sure. Could it be C) Evolutionary Development? I know that's where the requirements are continuously refined and updated.
upvoted 0 times
Nu
1 months ago
User 3: I'm not sure, but it does sound like the right phase to do it.
upvoted 0 times
...
Caitlin
2 months ago
Yeah, I agree. It makes sense to baseline the Prioritised Requirements List during Evolutionary Development.
upvoted 0 times
...
Yuonne
2 months ago
I think you might be right. That's when the requirements are finalized.
upvoted 0 times
...
...
Reuben
2 months ago
I think it's B) Foundations. That's where the requirements are defined and baselined, right?
upvoted 0 times
Lon
24 days ago
D) Deployment
upvoted 0 times
...
Marlon
25 days ago
C) Evolutionary Development
upvoted 0 times
...
Tracey
26 days ago
B) Foundations
upvoted 0 times
...
Alline
1 months ago
A) Feasibility
upvoted 0 times
...
...
Berry
2 months ago
Hmm, that makes sense too. It's important to have a solid foundation before evolving the requirements.
upvoted 0 times
...
Wei
3 months ago
I disagree, I believe it happens during Evolutionary Development.
upvoted 0 times
...
Berry
3 months ago
I think the Prioritised Requirements List is baselined during Foundations.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77