Resources are limited. The Sales Manager has two marketing assistants who

may be able to give a few hours a week between them to the project.

What action should the Project Manager take?

Show Suggested Answer Hide Answer
Suggested Answer: A

In the context of Agile Project Management, it is crucial to have clear commitments regarding team members' availability to ensure that project planning and execution can be as accurate and effective as possible. By securing a formal agreement on the hours the marketing assistants can dedicate to the project each week, the Project Manager can better plan tasks and allocate resources, thereby optimizing the team's capacity and ensuring that project timelines and deliverables are realistic and achievable.


The Agile Project Management (AgilePM) framework emphasizes the importance of clear communication, resource planning, and commitment from all team members to ensure project success. Having a formal agreement on availability helps in setting clear expectations and allows for more effective planning and utilization of resources within the constraints of the project, aligning with Agile principles of collaboration, adaptability, and iterative progress.

Contribute your Thoughts:

Vanda
2 months ago
Option C reminds me of that saying, 'Stretching a rubber band too far will only lead to it breaking.'
upvoted 0 times
...
Melina
2 months ago
Haha, Option B is like saying 'Let's just wing it and see what happens!' Not a very reliable strategy.
upvoted 0 times
...
Jacqueline
2 months ago
Option D sounds like a good idea too. Scheduling the marketing assistants at different times could help keep things organized.
upvoted 0 times
Milly
1 months ago
User 3: Scheduling the assistants at different times could also help with organization.
upvoted 0 times
...
Cecily
1 months ago
User 2: That sounds like a good idea. It will help with consistency.
upvoted 0 times
...
Natalie
1 months ago
User 1: I think we should try to secure formal agreement on how many hours the marketing assistants will spend on the project.
upvoted 0 times
...
...
Ruthann
2 months ago
I agree with Devora. A formal agreement is crucial to managing the limited resources effectively.
upvoted 0 times
Ronny
30 days ago
C) Make each Timebox as long as possible to ensure the marketing assistants have enough time to complete any work allocated to them within the boundaries of the Timebox.
upvoted 0 times
...
Jolene
1 months ago
B) Accept that members of the Solution Development Team will be inconsistent.
upvoted 0 times
...
Cherrie
2 months ago
A) Try to secure formal agreement as to how many hours per week the marketing assistants will spend on the project.
upvoted 0 times
...
...
Selma
2 months ago
I think scheduling the assistants to work at different times could also be a good idea to ensure continuity.
upvoted 0 times
...
Gene
3 months ago
I agree with Belen. It's important to have clarity on the marketing assistants' availability.
upvoted 0 times
...
Belen
3 months ago
I think the Project Manager should try to secure formal agreement on hours per week.
upvoted 0 times
...
Devora
3 months ago
Option A seems like the best approach. We need to get a formal agreement on the hours to ensure the project stays on track.
upvoted 0 times
Daron
2 months ago
I think option A is the way to go in this situation.
upvoted 0 times
...
Gladys
2 months ago
It's important to have a clear plan in place for the marketing assistants.
upvoted 0 times
...
Lovetta
2 months ago
I agree, we should definitely try to secure formal agreement on the hours.
upvoted 0 times
...
Laurel
2 months ago
Yes, that way we can make sure the project stays on track.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77