Question #: 78
Topic #: 3
[All CMQ-OE Questions]

Which of the following statements is true about using the plan-do-check-act (PDCA) methodology to make an improvement?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Glenn
11 days ago
Did someone say 'PDCA'? Sounds like a new dance craze to me! But in all seriousness, I think C is the answer.
upvoted 0 times
...
Michell
12 days ago
Hmm, I'm torn between A and C. I guess I'll go with C since it mentions the 'checking' process producing corrective actions.
upvoted 0 times
...
Justine
14 days ago
I'm going with B. The 'doing' step is where the actual work happens, so it's more important than the 'checking' process.
upvoted 0 times
...
Felix
18 days ago
D seems like the right choice. The PDCA cycle should continue until the desired results are achieved, even if it takes multiple iterations.
upvoted 0 times
Iola
3 days ago
I think C is also important because the checking process usually leads to corrective actions.
upvoted 0 times
...
Gerri
7 days ago
I agree, D is the correct choice. The process should continue until the desired results are achieved.
upvoted 0 times
...
...
Celia
1 months ago
I think C is the correct answer. The 'checking' process is crucial to identify areas for improvement and corrective actions.
upvoted 0 times
Hubert
4 days ago
Yes, the 'checking' process usually leads to corrective actions to achieve desired results.
upvoted 0 times
...
Tiffiny
7 days ago
I agree, the 'checking' process is crucial for identifying areas for improvement.
upvoted 0 times
...
Julianna
22 days ago
I think C is the correct answer.
upvoted 0 times
...
...
Detra
1 months ago
I disagree, I believe the answer is D.
upvoted 0 times
...
Oneida
1 months ago
I think the correct answer is C.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77