BCS Exam ISEB-PM1 Topic 10 Question 77 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 77
Topic #: 10
[All ISEB-PM1 Questions]

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Eun
4 months ago
Hmm, let me think... Ah yes, B) Qualitative risk analysis is the process that fits the bill. Probability and impact, baby!
upvoted 0 times
Denae
3 months ago
Quantitative risk analysis is also important, but for assessing priority based on occurrence probability and impact, B) Qualitative risk analysis is the way to go.
upvoted 0 times
...
Lisandra
3 months ago
I think it's important to prioritize risks based on their potential impact on project objectives. B) Qualitative risk analysis does just that.
upvoted 0 times
...
Glenn
4 months ago
I agree, B) Qualitative risk analysis is the way to go. It considers both occurrence probability and impact.
upvoted 0 times
...
...
Rodolfo
4 months ago
You know, when it comes to risk, I always say - go big or go home! Quantitative risk analysis is the way to party.
upvoted 0 times
Harley
3 months ago
Risk management planning is crucial to ensure all risks are properly addressed.
upvoted 0 times
...
Meaghan
3 months ago
I prefer to focus on risk identification first before diving into the analysis.
upvoted 0 times
...
Ashlee
3 months ago
I think qualitative risk analysis is also important to consider.
upvoted 0 times
...
Bobbye
4 months ago
I agree, quantitative risk analysis is definitely the way to go!
upvoted 0 times
...
...
Shonda
5 months ago
Yes, but qualitative analysis helps prioritize risks based on their potential impact on project objectives.
upvoted 0 times
...
Malcom
5 months ago
But isn't quantitative analysis more precise in assessing risk?
upvoted 0 times
...
Carol
5 months ago
I'm pretty sure B) is the right choice here. Gotta love that probability and impact assessment!
upvoted 0 times
Chanel
4 months ago
Yeah, it's all about assessing probability and impact on project objectives.
upvoted 0 times
...
Carlee
4 months ago
I think B) Qualitative risk analysis is the way to go.
upvoted 0 times
...
...
Fidelia
5 months ago
I agree with Dean, qualitative analysis considers both probability and impact.
upvoted 0 times
...
Carma
5 months ago
Easy peasy! Qualitative risk analysis is the way to go for assessing risk priority.
upvoted 0 times
Hubert
4 months ago
Definitely, it's all about assessing the probability and impact to prioritize our risks effectively.
upvoted 0 times
...
Annamae
4 months ago
Quantitative risk analysis is important too, but qualitative analysis gives us a good starting point.
upvoted 0 times
...
Tammara
4 months ago
It helps us understand the likelihood and impact of each risk on our project.
upvoted 0 times
...
Abel
5 months ago
I agree, qualitative risk analysis is essential for prioritizing risks.
upvoted 0 times
...
...
Dean
5 months ago
I think it's B) Qualitative risk analysis.
upvoted 0 times
...
Azzie
6 months ago
B) Qualitative risk analysis is the correct answer. It uses probability and impact to prioritize risks.
upvoted 0 times
Gwenn
5 months ago
Yes, that's correct. It assesses the priority of risks based on occurrence probability and impact.
upvoted 0 times
...
Doug
5 months ago
I think it's B) Qualitative risk analysis.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77