BCS Exam ISEB-PM1 Topic 3 Question 5 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 5
Topic #: 3
[All ISEB-PM1 Questions]

What are the components of the "triple constraint"?

Show Suggested Answer Hide Answer
Suggested Answer: D

The Project Management Triangle (called also Triple Constraint) is a model of the constraints of project management. It is often used to illustrate that project management success is measured by the project team's ability to manage the project, so that the expected results are produced while managing time and cost.

Like any human undertaking, projects need to be performed and delivered under certain constraints. Traditionally, these constraints have been listed as 'scope,' 'time,' and 'cost'. These are also referred to as the 'Project Management Triangle,' (also known as the 'Iron Triangle') where each side represents a constraint. One side of the triangle cannot be changed without affecting the others. A further refinement of the constraints separates product 'quality' or 'performance' from scope, and turns quality into a fourth constraint.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77