BCS Exam RE18 Topic 18 Question 2 Discussion

Actual exam question for BCS's RE18 exam
Question #: 2
Topic #: 18
[All RE18 Questions]

A set of requirements for a new online health information portal have been prioritized using

MoSCoW:

REQ#1: (S)

REQ#2: (C)

REQ#3: (S)

REQ#4: (M)

REQ#5: (M)

REQ#6: (C)

REQ#7: (W)

Only the minimum usable subset was approved for inclusion in the first iteration of the project. After the build for the first iteration began, it was estimated there was enough time to add two additional requirements, without negative impact on the project schedule.

Which two requirements will now be added to the first iteration build?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77