BICSI Exam RCDDv14 Topic 11 Question 47 Discussion

Actual exam question for BICSI's RCDDv14 exam
Question #: 47
Topic #: 11
[All RCDDv14 Questions]

A program with objectives trial impact a large segment of the population receives negative commentary from organizations representing the public interest What action should the program manager take first?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Aleta
3 months ago
I think discussing the issues with the governance board is important to determine next steps.
upvoted 0 times
...
Laurel
3 months ago
Haha, I bet the program manager is wishing they had a crystal ball right about now. Option B is the way to go, though.
upvoted 0 times
Jesusita
3 months ago
Hopefully, the program manager can address the issues effectively with this approach.
upvoted 0 times
...
Marjory
3 months ago
I agree. It's important to review the stakeholder register to assess the situation accurately before taking any further action.
upvoted 0 times
...
Elenora
3 months ago
Option B is definitely the best choice. The program manager needs to understand how the affected stakeholders can impact the program.
upvoted 0 times
...
...
Lucy
4 months ago
But shouldn't they also assess the risk of negative media coverage?
upvoted 0 times
...
Tom
4 months ago
B is the way to go. Stakeholder analysis is the foundation for dealing with this kind of PR nightmare.
upvoted 0 times
...
Lavonna
4 months ago
I'd say B as well. Can't just jump into action without assessing the power dynamics at play here.
upvoted 0 times
Paola
2 months ago
Let's make sure we're prepared before taking any action.
upvoted 0 times
...
Theola
2 months ago
Once we have that information, we can plan our next steps accordingly.
upvoted 0 times
...
Fausto
3 months ago
Agreed, we need to understand how they can impact the program.
upvoted 0 times
...
Asha
3 months ago
I think we should review the stakeholder register first.
upvoted 0 times
...
...
Sanda
4 months ago
Definitely go with B. Knowing the influence of those groups is key to managing the situation effectively.
upvoted 0 times
Latanya
3 months ago
D) Discuss the issues with the governance board to determine next steps
upvoted 0 times
...
Margot
4 months ago
A) Rework the stakeholder engagement plan to foster better relationships with the affected stakeholder groups
upvoted 0 times
...
Lauryn
4 months ago
B) Review the stakeholder register to determine the ability of the affected stakeholder group(s) to affect program outcomes
upvoted 0 times
...
...
Jody
4 months ago
I agree with Merri, building better relationships with stakeholders is crucial.
upvoted 0 times
...
Stevie
4 months ago
Option B seems like the logical first step. Gotta understand the stakeholder dynamics before making any moves.
upvoted 0 times
Natalya
3 months ago
True, that could have a big impact on the program's success.
upvoted 0 times
...
Fannie
3 months ago
I think we should also consider the risk of negative media coverage.
upvoted 0 times
...
Andree
4 months ago
Definitely, it sets the foundation for any further actions.
upvoted 0 times
...
Tambra
4 months ago
I agree, understanding the stakeholders is crucial.
upvoted 0 times
...
...
Merri
4 months ago
I think the program manager should rework the stakeholder engagement plan.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77