Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BICSI Exam RCDDv14 Topic 5 Question 34 Discussion

Actual exam question for BICSI's RCDDv14 exam
Question #: 34
Topic #: 5
[All RCDDv14 Questions]

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program'?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Hyman
6 months ago
I think option C is the best choice, to ensure both communication needs and benefits expectations are documented.
upvoted 0 times
...
Leota
7 months ago
I agree. The stakeholder's expectations should be included in the benefits management plan.
upvoted 0 times
...
Margurite
7 months ago
Yes, meeting with the stakeholder is important to ensure communication needs are documented.
upvoted 0 times
...
Carmela
7 months ago
I think the program manager should meet with the stakeholder.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77