A new program manager joins a mufti-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization

At the next stakeholder meeting, what should the program manager present to address their concerns?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Reyes
6 days ago
Is option A) Program charter even a real answer? That's like, the bare minimum. C) Business case and program roadmap is clearly the way to go.
upvoted 0 times
...
Kati
14 days ago
I'm torn between B) Program scope assessment results and C) Business case and program roadmap. Both could be useful, but I'd probably lean towards C).
upvoted 0 times
...
Edmond
16 days ago
D) Expected program benefits management plan seems like the most comprehensive option to address their concerns. Showing them the expected benefits is key.
upvoted 0 times
...
Elvis
17 days ago
I think the program scope assessment results could also be helpful in addressing stakeholders' concerns by showing them the current status and future direction of the program.
upvoted 0 times
...
Darnell
19 days ago
I think C) Business case and program roadmap is the way to go. Stakeholders need to understand the bigger picture and how the program aligns with the organization's goals.
upvoted 0 times
Ronny
24 hours ago
B: Agreed, that will help stakeholders understand the bigger picture and the benefits the program will bring.
upvoted 0 times
...
Margurite
11 days ago
A: We should definitely present the business case and program roadmap to show how the program aligns with the organization's goals.
upvoted 0 times
...
...
Reed
20 days ago
I agree with Annette. The business case and program roadmap will help stakeholders understand the purpose and benefits of the program.
upvoted 0 times
...
Annette
26 days ago
I think the program manager should present the business case and program roadmap to address the stakeholders' concerns.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77