CIMA Exam CIMAPRA19-E02-1 Topic 7 Question 26 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 26
Topic #: 7
[All CIMAPRA19-E02-1 Questions]

An experienced IT project manager provides the following advice about planning a new project:

"The project should start withaRequirements Analysis which should take 10 days. When this is finished Detailed Design (10 days) and Interface studies (15 days) can start at the same time. As soon as they are both complete Prototyping can start (30 days).

Prototyping is the predecessor of both Implementation (10 days) and Data Conversion (20 days).

Go-Live is the final activity (5 days) and follows when Implementation and Data Conversion are both complete."

Using critical path analysis which statements are correct.

Select ALL that apply.

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77