CIMA Exam CIMAPRO19-P01-1 Topic 3 Question 99 Discussion

Actual exam question for CIMA's CIMAPRO19-P01-1 exam
Question #: 99
Topic #: 3
[All CIMAPRO19-P01-1 Questions]

JRL manufactures two products from different combinations of the same resources. Unit selling prices and unit cost details for each product are as follows:

The optimal solution in the previous question shows that the shadow prices of skilled labour and direct material A are as follows:

Skilled labour $ Nil

Direct material A $11.70

Explain the relevance of these values to the management of JRL.

What is the additional contribution that can be earned?

Show Suggested Answer Hide Answer
Suggested Answer: A

References:


Contribute your Thoughts:

Ryan
2 months ago
Alright, time to put on my problem-solving hat. The key is to understand how the shadow prices relate to the additional contribution. I'll have to do some calculations to figure out the correct answer.
upvoted 0 times
Lavina
22 days ago
So, the additional contribution that can be earned would depend on these shadow prices. We need to calculate it to make an informed decision.
upvoted 0 times
...
Jade
24 days ago
Yes, the shadow price of direct material A is $11.70, which means it's the value of an additional unit of that resource in the optimal solution.
upvoted 0 times
...
Jamal
1 months ago
I think the shadow prices of skilled labour and direct material A are crucial for determining the additional contribution.
upvoted 0 times
...
...
Charlie
2 months ago
Okay, let me think this through. The shadow prices tell us the potential increase in contribution if we had more of those resources. With direct material A at $11.70, that sounds promising. *chuckles* I wonder if they'll throw in a free unicorn with the right answer.
upvoted 0 times
Gail
1 months ago
Haha, a free unicorn would definitely make the decision easier!
upvoted 0 times
...
Jutta
1 months ago
Direct material A at $11.70 means more profit potential.
upvoted 0 times
...
Glendora
2 months ago
The shadow prices help us see the impact on contribution with more resources.
upvoted 0 times
...
...
Nan
2 months ago
I believe the penalty value at which WRX would decide not to supply the major customer order in full is $4,825.
upvoted 0 times
...
Jenifer
3 months ago
Hmm, the question mentions the optimal solution, but it doesn't specify the details of that solution. I'll have to carefully examine the given information to determine the additional contribution that can be earned.
upvoted 0 times
Bobbye
1 months ago
I believe the penalty value at which WRX would decide not to supply the major customer order in full is $4,825. It's important to consider all these factors.
upvoted 0 times
...
Ronny
2 months ago
So, the additional contribution that can be earned is crucial for decision-making. We have to calculate it accurately.
upvoted 0 times
...
Mila
2 months ago
The shadow price of skilled labour is nil, but direct material A has a shadow price of $11.70.
upvoted 0 times
...
Fabiola
2 months ago
I think we need to focus on the shadow prices of skilled labour and direct material A to understand the relevance to JRL's management.
upvoted 0 times
...
...
Jodi
3 months ago
Yes, they help in determining the additional contribution that can be earned.
upvoted 0 times
...
Eugene
3 months ago
The shadow price of direct material A is $11.70, which means that if JRL could obtain an additional unit of this material, it would increase the company's contribution by $11.70. Seems like a good opportunity to maximize profits.
upvoted 0 times
Grover
2 months ago
User2
upvoted 0 times
...
Darrin
3 months ago
User1
upvoted 0 times
...
...
Nan
3 months ago
I think the shadow prices of skilled labour and direct material A are important for decision making.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77