Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIMA Exam CIMAPRO19-P01-1 Topic 8 Question 94 Discussion

Actual exam question for CIMA's CIMAPRO19-P01-1 exam
Question #: 94
Topic #: 8
[All CIMAPRO19-P01-1 Questions]

CDF is a manufacturing company within the DF group. CDF has been asked to provide a quotation for a contract for a new customer and is aware that this could lead to further orders. As a consequence, CDF will produce the quotation by using relevant costing instead of its usual method of full cost plus pricing. The following information has been obtained in relation to the contract: Material D 40 tons of material D would be required. This material is in regular use by CDF and has a current purchase price of $38 per ton. Currently, there are 5 tons in inventory which cost $35 per ton. The resale value of the material in inventory is $24 per ton.

Components 4,000 components would be required. These could be bought externally for $15 each or alternatively they could be supplied by RDF, another company within the DF manufacturing group. The variable cost of the component if it were manufactured by RDF would be $8 per unit, and RDF adds 30% to its variable cost to contribute to its fixed costs plus a further 20% to this total cost in order to set its internal transfer price. RDF has sufficient capacity to produce 2,500 components without affecting its ability to satisfy its own external customers. However, in order to make the extra 1,500 components required by CDF, RDF would have to forgo other external sales of $50,000 which have a contribution to sales ratio of 40%.

Labour hours 850 direct labour hours would be required. All direct labour within CDF is paid on an hourly basis with no guaranteed wage agreement. The grade of labour required is currently paid $10 per hour, but department W is already working at 100% capacity. Possible ways of overcoming this problem are: * Use workers in department Z, because it has sufficient capacity. These workers are paid $15 per hour. * Arrange for sub-contract workers to undertake some of the other work that is performed in department W. The sub-contract workers would cost $13 per hour.

Specialist machine The contract would require a specialist machine. The machine could be hired for $15,000 or it could be bought for $50,000. At the end of the contract if the machine were bought, it could be sold for $30,000. Alternatively, it could be modified at a cost of $5,000 and then used on other contracts instead of buying another essential machine that would cost $45,000. The operating costs of the machine are payable by CDF whether it hires or buys the machine. These costs would total $12,000 in respect of the new contract.

Supervisor The contract would be supervised by an existing manager who is paid an annual salary of $50,000 and has sufficient capacity to carry out this supervision. The manager would receive a bonus of $500 for the additional work.

Development time 15 hours of development time at a cost of $3,000 have already been worked in determining the resource requirements of the contract.

Fixed overhead absorption rate CDF uses an absorption rate of $20 per direct labour hour to recover its general fixed overhead costs. This includes $5 per hour for depreciation.

Calculate the relevant cost of the contract to CDF. You must present your answer in a schedule that clearly shows the relevant cost value for each of the items identified above. You should also explain each relevant cost value you have included in your schedule and why any values you have excluded are not relevant.

Ignore taxation and the time value of money.

Select all the true statements.

Show Suggested Answer Hide Answer
Suggested Answer: A, D, E

References:


Contribute your Thoughts:

Socorro
4 months ago
I disagree, Tomoko. The development cost has already been incurred and is not relevant for this contract.
upvoted 0 times
...
Paz
4 months ago
This question is like a treasure hunt, but instead of finding gold, we're searching for the relevant costs. I think the key is to focus on the variable costs and exclude the fixed overhead. The material cost, component cost, and direct labor cost are all relevant, as are the machine operating costs and the development cost. As for the total, I'm going to take a wild guess and say $84,990. But who knows, maybe the answer is hiding in plain sight and I'm just missing it.
upvoted 0 times
Staci
2 months ago
I'm going to go with the total relevant cost of $84,990 as well. Let's see if we're right!
upvoted 0 times
...
Tony
3 months ago
I think machine operating costs and development cost should also be included.
upvoted 0 times
...
Teri
3 months ago
Material cost, component cost, and direct labor cost are definitely relevant.
upvoted 0 times
...
Monte
3 months ago
I agree, we need to focus on the variable costs and exclude the fixed overhead.
upvoted 0 times
...
...
Tomoko
4 months ago
I believe the development cost is also a relevant cost.
upvoted 0 times
...
Linwood
4 months ago
Ah, the joys of relevant costing. Let's see, the material cost, component cost, and direct labor cost are all relevant. The machine operating costs and development cost are also relevant, but the general fixed overhead costs are not. As for the total relevant cost, I'd say it's around $94,000. Although, if I'm being honest, I'm just guessing at this point. Relevant costing is like a secret language that I'm still trying to learn.
upvoted 0 times
Katie
4 months ago
I think the material cost, component cost, and direct labor cost are definitely relevant for this contract.
upvoted 0 times
...
Ellsworth
4 months ago
I agree, relevant costing can be tricky to navigate.
upvoted 0 times
...
...
Yvonne
4 months ago
This question is like a puzzle, but I think I've got it figured out. The relevant costs are the material cost, the component cost, the direct labor cost, the machine operating costs, and the development cost. The general fixed overhead costs are not relevant. Hmm, I wonder if the answer is $104,320? That seems a bit high, but I could be wrong.
upvoted 0 times
...
Truman
4 months ago
Okay, let's see. The relevant costs are the material cost, the component cost, the direct labor cost, and the machine operating costs. The development cost is also relevant, but the general fixed overhead costs should be excluded. I think the total relevant cost is somewhere around $94,000.
upvoted 0 times
Brent
3 months ago
I believe the total relevant cost is around $94,000 as well.
upvoted 0 times
...
Horace
4 months ago
I think we should exclude the general fixed overhead costs from the total relevant cost.
upvoted 0 times
...
Dorethea
4 months ago
I agree, the material cost, component cost, direct labor cost, machine operating costs, and development cost are all relevant.
upvoted 0 times
...
...
Hubert
4 months ago
I agree with you, Thaddeus. The machine is essential for the contract.
upvoted 0 times
...
Thaddeus
4 months ago
I think the machine operating costs is a relevant cost.
upvoted 0 times
...
Mitsue
4 months ago
Hmm, this is a tricky one. I think the relevant costs here are the material cost, the component cost, and the direct labor cost. The machine operating costs and the development cost are also relevant, but the general fixed overhead costs shouldn't be included in the relevant cost calculation.
upvoted 0 times
Chauncey
3 months ago
So, the total relevant cost should be the sum of all these costs, right?
upvoted 0 times
...
Kimberlie
3 months ago
I'm not sure about the general fixed overhead costs, I think those might not be relevant for this calculation.
upvoted 0 times
...
Rosio
3 months ago
I think the machine operating costs and development cost should also be included in the relevant cost calculation.
upvoted 0 times
...
Amber
4 months ago
I agree, the material cost, component cost, and direct labor cost are definitely relevant.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77