A procurement organisation is keen to encourage innovation available within the supply market in the execution of an upcoming significant contract opportunity. A team member suggests that the specification should define the performance indicators so that supplier's solution can be checked against them. Which of the following will enable the organisation to achieve this goal?
The buying organisation is keen to encourage innovation so they should use the outcome or output based specification. In an outcome-based specification, umbrella statements like 'good quality', 'ambient temperature', 'convenient way' are often used. This may confuse the suppliers, and it's hard to check the solution that supplier offers. On the other hand, ouput-based specifications often include measurable requirements. For example, a specification for air conditioning system states that the system should maintain the room temperature at 19-24 degrees Celsius. Therefore, output specification is more appropriate in this case.
LO 3, AC 3.1
Lenny
5 months agoTiara
5 months agoMiles
5 months agoLashonda
6 months agoEdda
5 months agoAlise
5 months agoJanessa
5 months agoStaci
5 months agoDona
5 months agoAlline
6 months agoStevie
6 months agoFletcher
5 months agoShelia
6 months agoNell
6 months agoSalome
6 months agoSang
6 months agoJoanna
6 months agoKenneth
6 months agoLarae
6 months agoDaniela
7 months ago