Product development consists of various stages, including planning and analysis, design develop-ment, pre-production, production and maintenance. At which stages the opportunities for cost re-duction will be the greatest?

1. Planning stage

2. Pre-design stage

3. Detail design stage

4. Production stage

5. Logistics support stage

Show Suggested Answer Hide Answer
Suggested Answer: C

Writing a specification and then procuring and using the product or service has a number of stages. The further on in the process you are, the less potential there is for cost reductions. Therefore, opportunities for cost reduction will be greatest in the two first stages: planning stage and pre-design stage.

LO 3, AC 3.1


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77