Question #: 5
Topic #: 5
[All L4M3 Questions]

A manufacturing company signed a contract with a raw material supplier. The contract includes a clause on liquidated damages in case of late delivery. Purchaser was obliged to pay after 30 days from delivery. Eventually raw material was delivered 1 week later than initial plan due to supplier's slow production process. There is no defect in the delivered batch. Which of the following can be claimed by the manufacturing company?

Show Suggested Answer Hide Answer
Suggested Answer: B

In certain circumstances, where two parties have monetary debts against each other, the right to set-off may arise. A right of set-off allows a (''Party 1'') to take into account the amount owed to it by the second party (''Party 2'') against any amount owed by Party 1 to Party 2, each party must be a debtor and a creditor.

Common law provides the key features that must be present for set-off to arise are;

1. mutuality of debts (each party must be the sole beneficial owner of the debt it is owed and the sole person liable for the debt it owes)

2. the claims each party has must be for non-payment of money

The common law provisions of set-off can be greatly enhanced by the inclusion of a contractual right to set-off (this is discussed further below) so that set-off is applicable in a greater range of situations. If you envisage set-off being a useful right it is not advisable to rely on the implied ability to use it (via common law or equitable set-off). Common law and equitable set-off are subject to various conditions and limitation however, a contractual right of set-off can be drafted to ensure parties are able to agree exactly how and when set-off should be applied.

In the above scenario, the supplier owes the manufacturer the payment for damages, while the manufacturer owes the supplier the payment for goods. This is mutuality of debts, which leads to right of set off.


- Set-off on the right foot: a practical guide to set-off

- CIPS study guide page 158-159

LO 3, AC 3.2

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77