Kirsty is designing a specification for a new contract and wants to include some qualitive KPIs for the new supplier, as well as quantitative. Which of the following could she include? Select TWO.

Show Suggested Answer Hide Answer
Suggested Answer: B, C

The correct answers are information sharing and trust. Further qualitative KPIs are listed on p.102. Deliveries in full and on time would be a quantitative KPI and early supplier involvement is not a KPI at all.


Contribute your Thoughts:

Becky
5 months ago
'Information sharing' too. It's more about collaboration.
upvoted 0 times
...
Erasmo
5 months ago
Yeah, 'Trust' seems qualitative. It's about working relations.
upvoted 0 times
...
Lizette
5 months ago
I'd say 'Trust' and 'Information sharing'.
upvoted 0 times
...
Pamela
6 months ago
So, which ones could be the qualitative KPIs?
upvoted 0 times
...
Becky
7 months ago
Right. She wants both qualitative and quantitative KPIs.
upvoted 0 times
...
Erasmo
7 months ago
Kirsty is designing a specification for a new contract.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77