Question #: 39
Topic #: 1
[All L5M3 Questions]

Which of the following conflict resolution styles involves a strict timeline and is commonly used within the construction industry?

Show Suggested Answer Hide Answer
Suggested Answer: B

Adjudication has strict timescales (this is one of the advantages of using this conflict resolution method). It has roots in the construction industry and has been widely used since the 1990s. See p.76 for more information


Contribute your Thoughts:

Truman
2 months ago
Litigation? No way, that's way too messy. Gotta be adjudication for that sweet, sweet construction industry.
upvoted 0 times
...
Rosita
2 months ago
I heard construction workers love a good timeline, so my money's on B. Adjudication.
upvoted 0 times
Evelynn
21 days ago
I agree, having a set timeline can help keep things on track in the construction industry.
upvoted 0 times
...
Zona
25 days ago
Yeah, adjudication seems like the best fit for resolving conflicts quickly.
upvoted 0 times
...
Lyndia
1 months ago
I think you're right, construction projects always have strict deadlines.
upvoted 0 times
...
...
Carolann
2 months ago
I'm not sure, but I think conciliation might also be a good option for resolving conflicts quickly.
upvoted 0 times
...
Melvin
2 months ago
I agree with Doyle, adjudication makes sense for construction projects with strict timelines.
upvoted 0 times
...
Doyle
2 months ago
I think the answer is B) adjudication.
upvoted 0 times
...
Tawanna
3 months ago
Adjudication sounds like a fancy way to say 'let the experts handle it'.
upvoted 0 times
Blondell
1 months ago
D) litigation
upvoted 0 times
...
Willard
2 months ago
C) arbitration
upvoted 0 times
...
Brandon
2 months ago
B) adjudication
upvoted 0 times
...
Laquanda
2 months ago
A) conciliation
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77