CompTIA Exam PK0-004 Topic 1 Question 11 Discussion

Actual exam question for CompTIA's PK0-004 exam
Question #: 11
Topic #: 1
[All PK0-004 Questions]

A project manager at a projectized organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits

and jeopardizes the commitment date.

Which of the following should the project manager do NEXT?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77