Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-004 Topic 1 Question 21 Discussion

Actual exam question for CompTIA's PK0-004 exam
Question #: 21
Topic #: 1
[All PK0-004 Questions]

A project team member states that the tasks identified in the project schedule for the week greatly exceed the number of available hours for the week.

Which of the following activities would have allowed the project manager to identify and correct this issue in advance?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77