CompTIA Exam PK0-005 Topic 2 Question 34 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 34
Topic #: 2
[All PK0-005 Questions]

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

Show Suggested Answer Hide Answer
Suggested Answer: B

The Scrum team should break the stories into workable items that can be completed within one sprint, which is a time-boxed period of 7 to 30 days, during which the team delivers a potentially releasable product increment. Breaking the stories into smaller and more manageable items can help the team to estimate them more accurately, plan them more effectively, and deliver them more reliably. Breaking the stories also aligns with the agile principle of delivering working software frequently and satisfying the customer through early and continuous delivery of valuable software.

The other options are not the best steps for the Scrum team to take next. Assigning more resources to complete similar stories in the future may not solve the problem of underestimation, and may introduce additional complexity and communication overhead. Extending the sprint duration when required with the approval of the product owner may compromise the consistency and predictability of the Scrum process, and may delay the feedback and validation from the stakeholders. Releasing the current progress into production and carrying over the rest of the code for the next sprint may result in an incomplete or unstable product increment, and may violate the definition of done, which is a shared understanding of the quality criteria that the product increment must meet. Reference = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 5: Project Scope Management1; CompTIA Project+ Certification Study Guide, 3rd Edition, Chapter 5: Project Scope Management2; The 3 Scrum Roles and Responsibilities Explained3; Implementation of Scrum - 7 Steps for an Effective Process4


Contribute your Thoughts:

Eden
1 months ago
Wow, D) really? Releasing partial code? That's like trying to ship a car with no wheels. I'll stick with B), thanks.
upvoted 0 times
Kip
7 days ago
Assigning more resources may not always be the solution.
upvoted 0 times
...
Barbra
9 days ago
It's important to focus on completing tasks within one sprint.
upvoted 0 times
...
Lucia
16 days ago
Breaking stories into workable items is a better approach.
upvoted 0 times
...
Yen
1 months ago
I agree, releasing partial code is risky.
upvoted 0 times
...
...
Terina
2 months ago
B) Break the stories into workable items that can be completed within one sprint. Trying to fit a story that's too big into a single sprint is just asking for trouble.
upvoted 0 times
...
Lera
2 months ago
D) Release the current progress into production and carry over the rest of the code for the next sprint. Might as well ship what we have and pick up the rest later.
upvoted 0 times
...
Alverta
2 months ago
C) Extend the sprint duration when required with the approval of the product owner. Completing the story should be the priority, even if it means adjusting the sprint timeline.
upvoted 0 times
...
Johna
2 months ago
B) Break the stories into workable items that can be completed within one sprint. This seems like the best approach to avoid similar issues in the future.
upvoted 0 times
...
Coleen
2 months ago
I'm going with D. Ship it and let the users find the bugs. That's what quality assurance is for, right?
upvoted 0 times
...
Bulah
2 months ago
B, definitely B. Wouldn't want to end up like the developer in the question, stuck in a sprint-long story black hole.
upvoted 0 times
Farrah
15 days ago
Let's make sure to communicate with the product owner about the changes we plan to make.
upvoted 0 times
...
Noelia
18 days ago
It's important to learn from this experience and adjust our approach for future sprints.
upvoted 0 times
...
Cheryll
22 days ago
Agreed, that way we can ensure each item is completed within the sprint.
upvoted 0 times
...
Maybelle
25 days ago
Yes, breaking the stories into smaller items is definitely the way to go.
upvoted 0 times
...
...
Jody
2 months ago
A? Really? Throwing more resources at the problem? That's like trying to put out a fire with a flamethrower.
upvoted 0 times
...
Tequila
2 months ago
C is the obvious choice. Extend the sprint, get the job done, and make the product owner happy. Scrum is all about flexibility, after all.
upvoted 0 times
...
Merilyn
2 months ago
I don't know, D looks tempting. Ship what we have and worry about the rest later. That's how we get things done around here!
upvoted 0 times
...
Clement
2 months ago
B seems like the way to go. Break those stories down and make them more manageable. That's the Agile way, right?
upvoted 0 times
Alita
26 days ago
Agreed, it's important to have manageable tasks to ensure successful completion in each sprint.
upvoted 0 times
...
Stevie
1 months ago
It will help the team better estimate and complete the work within a single sprint.
upvoted 0 times
...
Royal
2 months ago
Yes, breaking down the stories into smaller tasks is definitely the Agile way to go.
upvoted 0 times
...
...
Denny
2 months ago
But what if we need more time? Shouldn't we extend the sprint duration?
upvoted 0 times
...
Scot
2 months ago
I agree with Glen. It will help us better estimate and complete the work.
upvoted 0 times
...
Glen
3 months ago
I think we should break the stories into workable items.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77