Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-005 Topic 3 Question 37 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 37
Topic #: 3
[All PK0-005 Questions]

A project manager is using an agile methodology to lead the implementation of several features that should be developed concurrently. Which of the following items should the project manager view as a concern?

Show Suggested Answer Hide Answer
Suggested Answer: C

Agile methodologies emphasize flexibility and iterative progress, so strict deadlines can be a concern. They may limit the team's ability to adapt and respond to change, as emphasized by CompTIA Project+ in agile project management principles.


Contribute your Thoughts:

Dell
5 days ago
I agree with Tiara. C is the right answer here. Agile is all about being adaptable, and a fixed deadline from stakeholders could really throw a wrench in that.
upvoted 0 times
...
Carrol
5 days ago
But what about option C? If the stakeholders have provided a specific deadline, that could also be a concern for the project manager.
upvoted 0 times
...
Niesha
14 days ago
I agree with Chandra, if the team can only meet weekly, it might slow down the development process.
upvoted 0 times
...
Chandra
15 days ago
I think the project manager should be concerned about option B.
upvoted 0 times
...
Tiara
19 days ago
I think the correct answer is C. The stakeholders providing a specific deadline is a concern for an agile project manager since it can limit the flexibility and iterative nature of the agile process.
upvoted 0 times
Brandee
10 days ago
B: Yeah, it goes against the whole idea of adapting to change.
upvoted 0 times
...
Mitsue
12 days ago
A: I think it's C too. A strict deadline can be a challenge in agile.
upvoted 0 times
...
...

Save Cancel