Question #: 23
Topic #: 4
[All PK0-005 Questions]

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?

Show Suggested Answer Hide Answer
Suggested Answer: C

Smoothing is a conflict resolution technique where the project manager emphasizes areas of agreement and downplays the areas of difference. By focusing on common ground and minimizing the importance of the conflicting points, the project manager aims to reduce the tension and encourage cooperation among team members. This approach is often used for minor disagreements where maintaining harmony is more important than resolving the conflict itself.


Contribute your Thoughts:

Thaddeus
5 months ago
Smoothing, huh? Sounds like the project manager is trying to avoid a little team drama. Gotta keep those egos in check, am I right?
upvoted 0 times
Kati
4 months ago
A) Compromising
upvoted 0 times
...
Donte
4 months ago
C) Smoothing
upvoted 0 times
...
Lucy
4 months ago
D) Collaborating
upvoted 0 times
...
Micheline
4 months ago
A) Compromising
upvoted 0 times
...
...
Marge
5 months ago
A) Compromising is the best option. Both team members can give a little and find a middle ground that works for everyone.
upvoted 0 times
...
Danilo
5 months ago
I'm going with B) Forcing. Sometimes you just have to put your foot down and make the team do it your way. That's what a project manager is for, right?
upvoted 0 times
Carol
4 months ago
I agree, compromising might also be a good option. It's about finding a middle ground that satisfies both team members.
upvoted 0 times
...
Allene
5 months ago
I think D) Collaborating would be a better approach. It's important to work together and find a solution that everyone can agree on.
upvoted 0 times
...
...
Alana
5 months ago
D) Collaborating is the way to go. The team members need to work together to find a solution, not just sweep the disagreement under the rug.
upvoted 0 times
Janey
5 months ago
D) Collaborating is definitely the best approach. Working together can lead to a more effective solution.
upvoted 0 times
...
Ceola
5 months ago
A) Compromising might be a good option too. Finding a middle ground could help resolve the disagreement.
upvoted 0 times
...
...
Lili
6 months ago
I agree with Avery. Collaborating would help find a solution that satisfies both team members.
upvoted 0 times
...
Casey
6 months ago
C) Smoothing seems like the obvious choice here. Emphasizing agreement and downplaying differences is exactly what smoothing is all about.
upvoted 0 times
Kent
6 months ago
D) Collaborating
upvoted 0 times
...
Wilbert
6 months ago
A) Compromising
upvoted 0 times
...
Ronnie
6 months ago
C) Smoothing
upvoted 0 times
...
Aleta
6 months ago
Agreed, it will help us focus on our common ground and find a solution.
upvoted 0 times
...
Roosevelt
6 months ago
A) Compromising
upvoted 0 times
...
Reynalda
6 months ago
I think we should use the smoothing technique to address our disagreement.
upvoted 0 times
...
...
Avery
7 months ago
I think the project manager should use Collaborating.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77