Eccouncil Exam 712-50 Topic 1 Question 51 Discussion

Actual exam question for Eccouncil's 712-50 exam
Question #: 51
Topic #: 1
[All 712-50 Questions]

As the CISO, you are the project sponsor for a highly visible log management project. The objective of the project is to centralize all the enterprise logs into a security information and event management (SIEM) system. You requested the results of the performance quality audits activity.

The performance quality audit activity is done in what project management process group?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77