Exin Exam CDCS Topic 1 Question 5 Discussion

Actual exam question for Exin's CDCS exam
Question #: 5
Topic #: 1
[All CDCS Questions]

A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.

What type of generators should be installed?

Show Suggested Answer Hide Answer
Suggested Answer: B

In areas with frequent and extended power outages, continuous generators with at least an N+1 configuration are necessary to ensure consistent power availability. Continuous generators are designed for prolonged operation, making them suitable for scenarios where utility power is frequently unavailable, as in this case with outages exceeding 650 hours per year. An N+1 configuration ensures redundancy, which is critical for maintaining uptime in a high-availability data center.

Detailed Explanation:

Continuous generators provide reliable power over long durations, unlike standby generators, which are intended only for short-term use. The N+1 configuration ensures that there is always an additional generator available in case of failure, thus maintaining power supply even if one generator goes offline.

EPI Data Center Specialist References:

EPI best practices recommend continuous generators with redundancy for data centers located in areas with high power instability to maintain reliability and continuous operation.


Contribute your Thoughts:

Destiny
1 months ago
Haha, option D sounds like something a power company executive would propose - 'Just run the generators all the time, it'll be fine!' Yeah, right, and I have a bridge to sell you too.
upvoted 0 times
...
Kristeen
1 months ago
I'm not sure why anyone would choose option D. Continuous generators without an N+1 configuration? That's just asking for trouble when one of them inevitably goes down.
upvoted 0 times
Melodie
14 days ago
I agree, having a combination of generators with extra capacity is definitely the safer option
upvoted 0 times
...
Ronny
17 days ago
C) A combination of standby-, prime-, and continuous-generators, as the duration of the power outage is unpredictable. The total available capacity of the generators should be at least 500% of the data center load
upvoted 0 times
...
Hester
18 days ago
A) Standby generators should be installed in at least an N+1 configuration
upvoted 0 times
...
...
Desmond
1 months ago
I agree with Luis, having a combination of standby, prime, and continuous generators makes sense to ensure continuous power supply.
upvoted 0 times
...
Delmy
1 months ago
I agree, C is the best choice. The data center needs a robust and reliable power solution to ensure continuous operations, and the 500% capacity recommendation sounds like a sensible approach.
upvoted 0 times
...
Luis
1 months ago
I think option C is the best choice because the power outage duration is unpredictable.
upvoted 0 times
...
Hyman
1 months ago
Option C seems the most appropriate. With such frequent power outages, a combination of different generator types would provide the required redundancy and flexibility to handle the unpredictable duration of the outages.
upvoted 0 times
Jamal
7 days ago
Yes, having a total capacity of at least 500% of the data center load would ensure that the generators can handle the outages effectively.
upvoted 0 times
...
Tonette
7 days ago
Yes, having a total capacity of at least 500% of the data center load would ensure that the generators can handle the outages effectively.
upvoted 0 times
...
Stephaine
9 days ago
It's important to have enough capacity to handle the frequent power outages in that area.
upvoted 0 times
...
Alana
10 days ago
It's important to have enough capacity to handle the frequent power outages in that area.
upvoted 0 times
...
Lauran
23 days ago
Having a combination of standby, prime, and continuous generators would definitely provide the needed flexibility.
upvoted 0 times
...
Lavonda
24 days ago
Having a combination of standby, prime, and continuous generators would definitely provide the needed flexibility.
upvoted 0 times
...
Stephane
1 months ago
I agree, option C seems like the best choice for this situation.
upvoted 0 times
...
Tina
1 months ago
I agree, option C seems like the best choice for this situation.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77