Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Exin Exam EX0-103 Topic 1 Question 1 Discussion

Actual exam question for Exin's EX0-103 exam
Question #: 1
Topic #: 1
[All EX0-103 Questions]

What should planning for new or changed services include?

Show Suggested Answer Hide Answer
Suggested Answer: A

A . Correct. When planning new or changed services it should be considered how this affects the budget and workload.

B . Incorrect. Major non-conformities to all Underpinning Contracts are not relevant to planning for new or changed services.

C . Incorrect. Recent Problems and Known Errors in the desktop environment have normally no relation to planning for new or changed services.

D . Incorrect. This indicates the Capacity growth for current applications, it does not need to provide any relevant information for new or changed services.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77