GAQM Exam APM-001 Topic 3 Question 65 Discussion

Actual exam question for GAQM's APM-001 exam
Question #: 65
Topic #: 3
[All APM-001 Questions]

The probability and impact matrix is primarily used to:

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Michal
14 days ago
C is the way to go. Unless you're trying to become a professional risk analyst, in which case, I'd suggest a career change. Just kidding! Or am I?
upvoted 0 times
Domonique
4 days ago
C) Evaluate each risk's importance and priority during Perform Qualitative Risk Analysis.
upvoted 0 times
...
...
Virgina
29 days ago
Hmm, I was leaning towards D, but C makes more sense. I need to brush up on my risk management knowledge!
upvoted 0 times
Jaclyn
1 days ago
Yeah, D is more about defining and comparing impacts.
upvoted 0 times
...
Vivan
2 days ago
I agree, C is about evaluating importance and priority of risks.
upvoted 0 times
...
Shanice
16 days ago
I think C is the correct answer.
upvoted 0 times
...
...
Skye
1 months ago
Definitely C. It's all about assessing the qualitative aspects of risks, not the quantitative ones.
upvoted 0 times
Glory
2 days ago
It's important to evaluate each risk's importance and priority during risk analysis.
upvoted 0 times
...
Tonette
7 days ago
Yes, it helps us understand the qualitative aspects of risks better.
upvoted 0 times
...
Staci
16 days ago
I agree, assessing the importance and priority of risks is crucial.
upvoted 0 times
...
...
Stefania
1 months ago
I think C is the correct answer. The probability and impact matrix is a key tool in qualitative risk analysis to evaluate the importance and priority of each risk.
upvoted 0 times
Skye
11 days ago
I see your point. C does make sense for evaluating each risk's importance and priority.
upvoted 0 times
...
Elinore
16 days ago
Actually, it's C. The matrix is used during Perform Qualitative Risk Analysis to evaluate risk importance.
upvoted 0 times
...
Stefania
21 days ago
I think it's B. The matrix is used to develop a risk register for planning.
upvoted 0 times
...
Viva
1 months ago
I agree, C is the correct answer. The matrix helps evaluate each risk's importance and priority.
upvoted 0 times
...
...
Justine
2 months ago
I believe it is used to evaluate each risk's importance and priority during Perform Qualitative Risk Analysis.
upvoted 0 times
...
Elbert
2 months ago
What do you think the probability and impact matrix is primarily used for?
upvoted 0 times
...