Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Genesys Exam GE0-806 Topic 3 Question 80 Discussion

Actual exam question for Genesys's GE0-806 exam
Question #: 80
Topic #: 3
[All GE0-806 Questions]

An agent is scheduled to start a shift at 12:00 PM and the Start Before threshold is set to 5. Ifthe agent starts the shift at 11:54 AM. They will be considered________.

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Lai
6 months ago
So it seems we have mixed opinions on this question. We should review the guidelines to confirm the correct answer.
upvoted 0 times
...
Samuel
7 months ago
I also think it would be considered adherent, as long as they are within the threshold time.
upvoted 0 times
...
Ming
7 months ago
I'm not sure, but I think the correct answer is A) Adherent because they are within the threshold.
upvoted 0 times
...
Johanna
7 months ago
I think it would be considered an exception since it's only 6 minutes before the shift start time.
upvoted 0 times
...
Hildegarde
7 months ago
I disagree, I believe they would be considered severely non-adherent because they are starting before the threshold.
upvoted 0 times
...
Lai
7 months ago
I think if the agent starts at 11:54 AM, they will be considered adherent.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77