HP Exam HPE0-S22 Topic 2 Question 13 Discussion

Actual exam question for HP's HPE0-S22 exam
Question #: 13
Topic #: 2
[All HPE0-S22 Questions]

A customer requires a server infrastructure update for its Hadoop HBase solution. The HBase maximum

dataset size will be 120TB.

To host HBase, the architect is planning three HPE Moonshot 1500 chassis fully populated with cartridges.

The populated chassis provide the following in total:

- 135 processors with four 2.9GHz cores each

- 4.23TB RAM

- 64.8TB local storage on SSDs

An aspect of the design is under provisioned and is likely to cause performance to degrade to one-tenth or even one-hundredth of its potential.

How can the architect resolve this problem?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77