HP Exam HPE0-S59 Topic 5 Question 40 Discussion

Actual exam question for HP's HPE0-S59 exam
Question #: 40
Topic #: 5
[All HPE0-S59 Questions]

Your customer has 6 logical enclosures spanning 18 HPE Synergy frames. The customer needs to add one more logical enclosure based on 5 HPE Synergy frames

How will this change impact the customer environment?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Marjory
5 months ago
Haha, this reminds me of that time I had to explain to my boss why we needed to buy more RAM for the servers. Guess the customer's got the same problem, just with frames instead of RAM!
upvoted 0 times
...
Ollie
5 months ago
I'm going with Option B. The customer needs to expand the management ring capacity to accommodate the new logical enclosure.
upvoted 0 times
...
Ronnie
5 months ago
Option C seems logical. The maximum number of frames in a single management ring is reached, so a new management ring is required for the additional logical enclosure.
upvoted 0 times
Veda
3 months ago
Yes, creating a new management ring will help maintain the efficiency and performance of the customer environment.
upvoted 0 times
...
Florinda
4 months ago
That makes sense. It's important to ensure the setup can handle the additional frames without any issues.
upvoted 0 times
...
Clarence
4 months ago
Option C seems logical. The maximum number of frames in a single management ring is reached, so a new management ring is required for the additional logical enclosure.
upvoted 0 times
...
Annice
4 months ago
Yes, creating a new management ring will help maintain efficiency and prevent any potential issues with the new logical enclosure.
upvoted 0 times
...
Shakira
4 months ago
That makes sense. It's important to ensure the setup is properly managed and organized.
upvoted 0 times
...
Aleta
4 months ago
Option C seems logical. The maximum number of frames in a single management ring is reached, so a new management ring is required for the additional logical enclosure.
upvoted 0 times
...
...
Novella
5 months ago
Actually, the customer can add a new logical enclosure to an existing setup once all required licenses are added to HPE OneView and associated with the new frames. That seems like the best option.
upvoted 0 times
...
Devon
5 months ago
I believe the customer has to create a new management ring for the new logical enclosure because the maximum number of frames in a single management ring is reached.
upvoted 0 times
...
Skye
5 months ago
But what if the customer needs to expand the management ring capacity? Do they have to add HPE Composer 2 modules or add memory to reach 128GB per module?
upvoted 0 times
...
Krissy
5 months ago
I think the customer can add a new logical enclosure to the existing setup because the maximum number of logical enclosures in a single management ring is not reached.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77