Huawei Exam H12-223 Topic 1 Question 91 Discussion

Actual exam question for Huawei's H12-223 exam
Question #: 91
Topic #: 1
[All H12-223 Questions]

Which of the following statements regarding the operation window time for a software upgrade is false?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Vinnie
5 months ago
Because troubleshooting time must be reserved to handle any unexpected issues during the upgrade.
upvoted 0 times
...
Merri
5 months ago
But why do you think that?
upvoted 0 times
...
Vinnie
5 months ago
I disagree, I believe the answer is C.
upvoted 0 times
...
Johnson
5 months ago
Hmm, I'd say C is a bit of a no-brainer. Troubleshooting time is essential for any upgrade, right?
upvoted 0 times
Roy
4 months ago
B) It must be longer than the upgrade execution time.
upvoted 0 times
...
Ozell
4 months ago
A) It is determined by the accepted service interruption duration.
upvoted 0 times
...
...
Patria
5 months ago
B makes the most sense to me. The upgrade execution time should be shorter than the operation window.
upvoted 0 times
...
Laquita
5 months ago
Haha, D? Really? The customer is the one who's gonna be impacted, of course they need to know!
upvoted 0 times
Chau
4 months ago
Totally agree, communication with customers is key in these situations.
upvoted 0 times
...
Jeannine
4 months ago
Exactly, customers have the right to know about any potential service interruptions.
upvoted 0 times
...
Troy
4 months ago
Yeah, D is definitely false. Customers should be informed.
upvoted 0 times
...
Burma
4 months ago
D) Only network maintenance personnel need to be notified of the operation window time, while the customer does not.
upvoted 0 times
...
Haley
5 months ago
C) Troubleshooting time must be reserved.
upvoted 0 times
...
Slyvia
5 months ago
B) It must be longer than the upgrade execution time.
upvoted 0 times
...
Laticia
5 months ago
A) It is determined by the accepted service interruption duration.
upvoted 0 times
...
...
Merri
5 months ago
I think the answer is D.
upvoted 0 times
...
Alaine
6 months ago
Exactly, B is the correct answer. Gotta give yourself some buffer time in case things don't go as planned.
upvoted 0 times
...
Broderick
6 months ago
D is definitely false. The customer should be notified of the operation window time as well.
upvoted 0 times
Corazon
5 months ago
B) It must be longer than the upgrade execution time.
upvoted 0 times
...
Denise
5 months ago
A) It is determined by the accepted service interruption duration.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77