(single choice) Which of the following is the correct power-on sequence of the Huawei OceanStor 9000 big data storage system?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Jeannetta
6 months ago
That's a good point I see the logic in that sequence as well.
upvoted 0 times
...
Shelton
6 months ago
I personally think Cabinet-->Switch-->KVM--->Node is the best option for optimal performance.
upvoted 0 times
...
Meghann
7 months ago
But wouldn't it make more sense for the KVM to be powered on before the Node?
upvoted 0 times
...
Jeannetta
7 months ago
I disagree, I believe it is Cabinet-->Switch-->Node--->KVM.
upvoted 0 times
...
Meghann
7 months ago
I think the correct power-on sequence is Cabinet-->KVM-->Switch--->Node.
upvoted 0 times
...
Trina
8 months ago
Yes, it is.
upvoted 0 times
...
Cammy
8 months ago
Is that the correct power-on sequence?
upvoted 0 times
...
Trina
8 months ago
Cabinet-->Switch-->KVM--->Node
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77