IIBA Exam CCBA Topic 3 Question 11 Discussion

Actual exam question for IIBA's CCBA exam
Question #: 11
Topic #: 3
[All CCBA Questions]

You are the business analyst for your organization. Your current project is using a plan-driven approach for the requirements, business analysis, and monitoring. Which one of the following statements best describes the plan-driven approach to business analysis planning and monitoring?

Show Suggested Answer Hide Answer
Suggested Answer: B

The plan-driven approach has the most business analysis work at the beginning of the project or during the start of a project phase. This approach has a high amount of formality and detail for all areas of the business analysis duties, requirements gathering, and monitoring.

Answer, D is incorrect. This statement is not true about the plan-driven approach.

Answer, C is incorrect. This statement describes requirements prioritization.

Answer, A is incorrect. Plan-driven approaches typically discourage change and they work to refine the requirements over time to prevent errors and omissions.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!