IIBA Exam IIBA-AAC Topic 6 Question 37 Discussion

Actual exam question for IIBA's IIBA-AAC exam
Question #: 37
Topic #: 6
[All IIBA-AAC Questions]

A practice common to most agile approaches is to require that the items in the product backlog that are targeted to be delivered next, are:

Show Suggested Answer Hide Answer
Suggested Answer: B