ISC2 Exam CAP Topic 10 Question 85 Discussion

Actual exam question for ISC2's CAP exam
Question #: 85
Topic #: 10
[All CAP Questions]

You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Tricia
6 months ago
True, but I still think risks are the biggest issue. More overlap, more risk.
upvoted 0 times
...
Gracie
7 months ago
What about quality control concerns? Increasing the speed might impact quality.
upvoted 0 times
...
Audria
7 months ago
I agree. It introduces more uncertainty and potential errors.
upvoted 0 times
...
Gennie
7 months ago
I think risks would increase. Fast tracking means overlapping activities.
upvoted 0 times
...
Mi
7 months ago
Yeah, I did. Fast tracking can really complicate things.
upvoted 0 times
...
Belen
7 months ago
Hey, did anyone see that project management question? It’s a bit tricky.
upvoted 0 times
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77