A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
When you are hiring a third party to own risk, it is known as transference risk response.
Transference is a strategy to mitigate negative risks or threats. In this strategy, consequences and the ownership of a risk is transferred to a
third party. This strategy does not eliminate the risk but transfers responsibility of managing the risk to another party. Insurance is an
example of transference.
Answer B is incorrect. The act of spending money to reduce a risk probability and impact is known as mitigation.
Answer A is incorrect. Exploit is a strategy that may be selected for risks with positive impacts where the organization wishes to ensure
that the opportunity is realized.
Answer D is incorrect. When extra activities are introduced into the project to avoid the risk, this is an example of avoidance.