Part of your change management plan details what should happen in the change control system for your project. Theresa, a junior project

manager, asks what the configuration management activities are for scope changes. You tell her that all of the following are valid

configuration management activities except for which one?

Show Suggested Answer Hide Answer
Suggested Answer: D

Configuration item cost is not a valid activity for configuration management. Cost changes are managed by the cost change control system;

configuration management is concerned with changes to the features and functions of the project deliverables.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77