Which of the following describes the acceptable amount of data loss measured in time?

Show Suggested Answer Hide Answer
Suggested Answer: A

The Recovery Point Objective (RPO) describes the acceptable amount of data loss measured in time. It is the point in time to which data must

be recovered as defined by the organization. The RPO is generally a definition of what an organization determines is an 'acceptable loss' in a

disaster situation. If the RPO of a company is 2 hours and the time it takes to get the data back into production is 5 hours, the RPO is still 2

hours. Based on this RPO the data must be restored to within 2 hours of the disaster.

Answer B is incorrect. The Recovery Time Objective (RTO) is the duration of time and a service level within which a business process

must be restored after a disaster or disruption in order to avoid unacceptable consequences associated with a break in business continuity. It

includes the time for trying to fix the problem without a recovery, the recovery itself, tests and the communication to the users. Decision time

for user representative is not included. The business continuity timeline usually runs parallel with an incident management timeline and may

start at the same, or different, points.

In accepted business continuity planning methodology, the RTO is established during the Business Impact Analysis (BIA) by the owner of a

process (usually in conjunction with the Business Continuity planner). The RTOs are then presented to senior management for acceptance.

The RTO attaches to the business process and not the resources required to support the process.

Answer D is incorrect. The Recovery Time Actual (RTA) is established during an exercise, actual event, or predetermined based on

recovery methodology the technology support team develops. This is the time frame the technology support takes to deliver the recovered

infrastructure to the business.

Answer C is incorrect. The Recovery Consistency Objective (RCO) is used in Business Continuity Planning in addition to Recovery Point

Objective (RPO) and Recovery Time Objective (RTO). It applies data consistency objectives to Continuous Data Protection services.


Contribute your Thoughts:

Christiane
3 months ago
Oh, you're right. RTO is the correct answer then. Thanks for clarifying.
upvoted 0 times
...
Mirta
3 months ago
But RPO is about the acceptable amount of data loss, not the time it takes to recover.
upvoted 0 times
...
Christiane
3 months ago
I disagree, I believe it's B) Recovery Time Objective (RTO).
upvoted 0 times
...
Mirta
3 months ago
I think the answer is A) Recovery Point Objective (RPO).
upvoted 0 times
...
Tomas
3 months ago
You're right, RTO is the correct answer. It measures the time it takes to recover after a disaster.
upvoted 0 times
...
Emily
3 months ago
As a dedicated data enthusiast, I can say with confidence that the RPO is the only correct answer. Unless, of course, you're a fan of data-free living.
upvoted 0 times
...
Jamika
3 months ago
The RCO? What is this, a road safety exam? I'll stick with the RPO, thank you very much.
upvoted 0 times
...
Belen
4 months ago
Wait, is the RTA the time it takes to actually recover? That's a trick question if I ever saw one.
upvoted 0 times
Keneth
2 months ago
No problem, happy to help.
upvoted 0 times
...
Cecily
2 months ago
That makes sense, thanks for clarifying.
upvoted 0 times
...
Harris
2 months ago
Yes, RTA is the actual time it takes to recover.
upvoted 0 times
...
Dominga
2 months ago
D) Recovery Time Actual (RTA)
upvoted 0 times
...
Raina
2 months ago
C) Recovery Consistency Objective (RCO)
upvoted 0 times
...
Mari
2 months ago
B) Recovery Time Objective (RTO)
upvoted 0 times
...
Kristal
3 months ago
A) Recovery Point Objective (RPO)
upvoted 0 times
...
...
Stefany
4 months ago
But RPO measures the acceptable amount of data loss, not the time it takes to recover.
upvoted 0 times
...
Fatima
4 months ago
Hmm, the RPO is the key here. Can't lose more data than the RPO allows, right? Easy peasy.
upvoted 0 times
Chaya
2 months ago
That's correct. It helps in setting the limit for how much data can be lost in a disaster.
upvoted 0 times
...
Rodolfo
2 months ago
So, the RPO is like a safety net for data loss prevention.
upvoted 0 times
...
Art
3 months ago
Exactly, it's important to ensure that data loss does not exceed the RPO.
upvoted 0 times
...
Izetta
3 months ago
Yes, you're right. The RPO determines the maximum acceptable amount of data loss.
upvoted 0 times
...
...
Tomas
4 months ago
I disagree, I believe it's B) Recovery Time Objective (RTO).
upvoted 0 times
...
Stefany
4 months ago
I think the answer is A) Recovery Point Objective (RPO).
upvoted 0 times
...
Tula
4 months ago
The RPO is the acceptable amount of data loss measured in time, not the RTO. I'm pretty sure about this one.
upvoted 0 times
Eulah
3 months ago
It's important to understand the difference between RPO and RTO in data recovery.
upvoted 0 times
...
Natalie
4 months ago
Yes, the RPO is definitely not the same as the RTO.
upvoted 0 times
...
Karon
4 months ago
I agree, the RPO is the acceptable amount of data loss measured in time.
upvoted 0 times
...
...

Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77