John works as a security engineer for BlueWell Inc. He wants to identify the different functions that the system will need to perform to meet the documented mission/business needs. Which of the following processes will John use to achieve the task?
The Functional requirements are used to classify the different functions that the system will need to
perform to meet the documented
mission/business needs.
Answer option B is incorrect. The Performance requirements are the agreed-upon terms of how well
the system functions.
Answer option A is incorrect. The modes of operation defines the mode, such as training mode, pre-
production mode, etc.
Answer option D is incorrect. The Technical performance measures are key indicators of system
performance such as key critical measures of
effectiveness that will put the project at risk.