Which of the following individuals reviews and approves project deliverables from a QA perspective?
A quality assurance manager reviews and approves project deliverables from QA perspective. This is
usually accomplished by providing
guidance and assistance on process matters. A quality assurance manager reviews plans and
deliverables for compliance with applicable
standards.
Answer option B is incorrect. The system owner has the responsibility of informing the key officials
within the organization of the requirements
for a security C&A of the information system. He makes the resources available, and provides the
relevant documents to support the process.
Answer option A is incorrect. The Information systems security engineer (ISSE) is responsible for
reviewing the security aspects.
Answer option D is incorrect. A project manager is responsible for assuring the quality of the
deliverables in a project. A project manager is a
person who manages the project and assures that the final deliverables are made in the stipulated
time and with the defined quality.