Which of the following tasks describes the processes required to ensure that the project includes all
the work required, and only the work required, to complete the project successfully?
The estimate project scope is the first task of planning the effort process that describes the
processes required to ensure that the project
includes all the work required, and only the work required, to complete the project successfully. This
task is used to accurately describe the
deliverables expected from the project.
Answer option C is incorrect. Identify Resources and Availability is the second task of planning the
effort process. It helps to complete and
maintain a project and ensures that an organization has the proper people, skills, and other
resources.
Answer option A is incorrect. Identify Roles and Responsibilities is the third task of planning the
effort process that specifies the numbers and
types of personnel required to conduct the project.
Answer option B is incorrect. Develop Project Schedule is the fifth task of the planning the effort
process. It determines the start and finish
dates for project activities and tasks.