Question #: 60
Topic #: 5
[All ISSEP Questions]

Which of the following tasks describes the processes required to ensure that the project includes all

the work required, and only the work required, to complete the project successfully?

Show Suggested Answer Hide Answer
Suggested Answer: D

The estimate project scope is the first task of planning the effort process that describes the

processes required to ensure that the project

includes all the work required, and only the work required, to complete the project successfully. This

task is used to accurately describe the

deliverables expected from the project.

Answer option C is incorrect. Identify Resources and Availability is the second task of planning the

effort process. It helps to complete and

maintain a project and ensures that an organization has the proper people, skills, and other

resources.

Answer option A is incorrect. Identify Roles and Responsibilities is the third task of planning the

effort process that specifies the numbers and

types of personnel required to conduct the project.

Answer option B is incorrect. Develop Project Schedule is the fifth task of the planning the effort

process. It determines the start and finish

dates for project activities and tasks.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!