You are implementing a TAS for a system that has been live for over three years, using a hybrid waterfall and agile lifecycle. Live updates are made on a monthly basis.
There is no test team, with developers designing and executing unit and integration tests with some degree of automation and business analysts designing and executing manual tests at the system level. No formal test process exists, although the system has proved relatively stable for most of the time.
Unfortunately, the last two monthly releases were problematic with regression defects found in production. Your priority is the automation of functional regression tests at the system level, the budget for this has been approved by project stakeholders.
The Business Analysts have identified which test cases are most suitable for regression. You must use the organisation's long standing commercial automation tool which has passed a proof of concept in the platform for the system in question.
Which of the following suitability criteria needs the MOST attention for the TAS?
Assume that you are the TAE responsible for the correct functioning of a TAS, deployed in a test environment that consists of a few machines running the same version of the operating system. The TAS has been working and stable since its deployment, it has been used to run an automated test suite consisting of many similar automated test. The infrastructure team is planning to update the operating system on these machines by installing a new the service pack for security reasons. Since the vendor of the operating system assurance full backward compatibility, the infrastructure team assurance that there will be no impacts on the functioning of the TAS.
What is the BEST approach to confirm the correct functioning of the TAS in this scenario?
You have investigated a new tool which enables the modelling of the SUT and can then generate test cases either manually or automatically. You have convinced your managers that the best way forward is to conduct a pilot project for this tool. You need to select a project to use for the pilot. You have the choice of the following projects:
Project A: A two-year project that is critical to the business and is currently in the requirement phase. This project is for a new e-commerce web site and is mostly being developed ''in-house" although the payment system is being developed and delivered by a 3rd party provider.
Project B: A safety critical application for software to drive and park cars.
Project C: An upgrade to an important HR timesheet tracking application that will be available on a desktop and mobile application. This is a 1-month project developed in-house.
Project D The payment system from project A.
Which project would be BEST for the pilot?
The Test Automation Manager has asked you to provide a solution for collecting metrics from the TAS that measures code coverage every time the automated regression test pack is run. The metrics must be trend based to ensure that the scope of the regression test pack continues to reflect enhancements made to the SUT - coverage must not drop and should ideally increase. The solution must be as automated as possible to avoid unnecessary manual overheads and errors.
Which of the following approaches would BEST meet these requirements?
You are working as a TAE for a company who are re-designing their website. The new website provides information for customers and there are two minor features being developed:
1) Request a newsletter
2) Ability to contact the organisation with a question or comment
The website must be ''mobile friendly" and available on all major web browsers.
You have been tasked to provide an automated solution for web browsers only and to concentrate on the two minor features.
What would be a KEY challenge with automation in this context?
Lyla
6 days agoCassi
17 days agoAllene
22 days agoMargot
1 months agoMagda
2 months agoIsidra
2 months agoRoselle
2 months agoBrinda
3 months agoVanesa
3 months agoRosita
3 months agoLouvenia
3 months agoLauryn
4 months agoArlyne
5 months agoIzetta
5 months agoNguyet
6 months agoAron
6 months agoTenesha
6 months agoThea
7 months ago