Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft Exam MB-320 Topic 3 Question 34 Discussion

Actual exam question for Microsoft's MB-320 exam
Question #: 34
Topic #: 3
[All MB-320 Questions]

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item. This item has the following Lean setup:

* The setup uses a Lean schedule group with a throughput ratio = 2.

* The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.

* The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).

* The throughput is 10 per hour.

You need to set up a Discrete operation to mirror the item's production flow activity.

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel
az-700  pass4success  az-104  200-301  200-201  cissp  350-401  350-201  350-501  350-601  350-801  350-901  az-720  az-305  pl-300  

Warning: Cannot modify header information - headers already sent by (output started at /pass.php:70) in /pass.php on line 77