Microsoft Exam MB-330 Topic 2 Question 101 Discussion

Actual exam question for Microsoft's MB-330 exam
Question #: 101
Topic #: 2
[All MB-330 Questions]

A cement manufacturing company uses Dynamics 365 Supply Chain Management. The company has two manufacturing plants. On average, each production plant produces 300,000 bags of cement before it must shut down for maintenance.

The production controller must allocate the required resources during the maintenance period.

You need to configure the system to meet the controller's requirements.

Which two options should you configure? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

Joaquin
3 months ago
Hold up, I think we're forgetting the most important part - the cement bags. Clearly, the correct answer is Counters (D) to keep track of the 300,000 bags produced. Everything else is just fluff.
upvoted 0 times
...
Roselle
3 months ago
I'm going to go with Maintenance plans (B) and Maintenance requests (E). The question mentions the production controller needs to 'allocate the required resources', so I think setting up maintenance requests would be important.
upvoted 0 times
Tanesha
3 months ago
Yes, those options would definitely help in allocating the required resources during the maintenance period.
upvoted 0 times
...
Sherrell
3 months ago
I agree, Maintenance plans (B) and Maintenance requests (E) seem like the right options to configure.
upvoted 0 times
...
...
Tommy
3 months ago
I believe Attributes and Asset service levels should also be configured to ensure proper resource allocation.
upvoted 0 times
...
Rozella
3 months ago
Yeah, I agree with Judy. Attributes (A) and Counters (D) don't seem directly relevant to the scenario. Maintenance requests (E) might be useful, but not as the primary solution.
upvoted 0 times
Amber
3 months ago
Attributes (A) and Counters (D) could be useful in other scenarios, but not in this specific case.
upvoted 0 times
...
Jovita
3 months ago
I agree, those options would help in allocating resources efficiently during maintenance.
upvoted 0 times
...
Alpha
3 months ago
I think Maintenance plans (B) and Asset service levels (C) are the key options to configure.
upvoted 0 times
...
...
Felicidad
3 months ago
I agree with Mel. Maintenance plans will help in scheduling the maintenance period efficiently.
upvoted 0 times
...
Mel
4 months ago
I think we should configure Maintenance plans and Maintenance requests.
upvoted 0 times
...
Judy
4 months ago
Hmm, I think the correct options are Maintenance plans (B) and Asset service levels (C). It seems like the key is to set up the planned maintenance for the production plants.
upvoted 0 times
Quiana
2 months ago
Counters (D) may not directly contribute to allocating resources during maintenance periods.
upvoted 0 times
...
Talia
3 months ago
Attributes (A) and maintenance requests (E) are not as essential for meeting the controller's requirements.
upvoted 0 times
...
Peter
3 months ago
Yes, and configuring asset service levels (C) will help ensure that the necessary resources are allocated efficiently.
upvoted 0 times
...
Frank
3 months ago
I agree, setting up maintenance plans (B) is crucial to keep the production plants running smoothly.
upvoted 0 times
...
...