Oracle Exam 1Z0-1008 Topic 1 Question 3 Discussion

Actual exam question for Oracle's 1Z0-1008 exam
Question #: 3
Topic #: 1
[All 1Z0-1008 Questions]

Your customer has the following setups on the project plan type that they are using for their projects:

Use Task Planned Dates as Task Assignment Dates = Yes

Automatically Roll Up Task Planned Dates = Yes

Synchronize Task Transaction Dates with Planned Dates = No

With these setups in place, you perform the following actions:

1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.

2. Create another new subtask (Sub Task 2) after the previous action is saved.

What would the correct behavior of the application be after these actions? (Choose the best answer.)

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!