Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost of each asset. Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)
Ref:
Topic -- Asset Cost Allocation Methods: Explained
The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type. You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset
Spread Evenly
Equal allocation of cost to each asset