Oracle Exam 1Z0-1074-23 Topic 1 Question 1 Discussion

Actual exam question for Oracle's 1Z0-1074-23 exam
Question #: 1
Topic #: 1
[All 1Z0-1074-23 Questions]

You are establishing the cost for a make assembly. When we run Cost Rollup, it is not rolling up and the Assembly shows "0" cost. However, item costs are available for child (buy) components. In the review work order cost, we are able to see child components costs, but not the rollup cost of the assembly.

Identify two reasons this happened.

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

Kiera
6 months ago
Yes, I agree. The work definition being incomplete could also be a contributing factor.
upvoted 0 times
...
Lorita
6 months ago
I believe another reason could be that burdens have not been established for the item.
upvoted 0 times
...
Mozell
7 months ago
That could be a reason. Maybe there are outstanding purchase orders that have not been received.
upvoted 0 times
...
Kiera
7 months ago
I think the assembly item is marked as Perpetual Average costed.
upvoted 0 times
...

Save Cancel